A change order records agreement, not just extra work
A change may add work, delete work, substitute a material or revise the sequence or scope. It can increase the price, reduce it or leave it unchanged. It may also change the completion time. The important distinction is that the parties record their agreement on the change and any price or time adjustment.
This guide uses the unmodified AIA A201–2017 as a reference. Other forms, supplementary conditions and subcontracts may use different procedures and approval authority. Read the executed documents before deciding whether a field instruction, email or signed form authorizes your specific work. This is practical guidance, not legal advice.
From field event to an executed change
That is a practical workflow, not a rule that you may always refuse to proceed until a change order is signed. A valid construction change directive can require work to proceed before all terms are agreed. AIA A201–2017 addresses that distinction in §7.3. Keep the authorization question separate from the pricing question.
- Identify what changed and link the request to a drawing, instruction or documented event.
- Define the affected scope, location, inclusions and exclusions.
- Prepare a supported cost proposal and identify the potential schedule effect.
- Follow any required notice procedure separately from sending the price proposal.
- Obtain the agreement and signatures required by the contract.
- Update the change log, contract-value reconciliation, schedule and billing record as applicable.
What the free change order template includes
The original Magra template has fields for project, contract reference, parties, change number, scope and supporting documents, price reconciliation, time adjustment and signature details. It is a generic free Excel/PDF form, not the proprietary AIA G701 form, and it is not AIA-approved. Use the licensed contract form when your project requires it.
Write the scope so another person can understand what is being added or removed. Attach revised drawings or a clearly identified exhibit rather than relying on “as discussed.” State exclusions. Enter an agreed time adjustment deliberately; do not insert zero simply because the schedule review is unfinished. Avoid broad release wording unless the appropriate reviewer has approved its consequences.
Check the contract-value arithmetic
For the example, $500,000 + $20,000 + $8,000 = $528,000. Previously authorized changes should be reconciled to the executed change log. Do not treat an unagreed directive as an executed prior change simply to make the total look complete. AIA’s G701 instructions specifically distinguish previously authorized change orders from directive changes not yet agreed and recorded as change orders.
Pricing support may include labor hours and rates, material quantities and quotes, equipment, subcontractor quotations and permitted markups. Check the contract’s allowable cost and markup rules and avoid counting the same cost twice. An agreed change can be a credit; preserve the sign in your reconciliation.
| Illustrative example | Amount |
|---|---|
| Original contract sum | $500,000 |
| Previously authorized changes | $20,000 |
| Contract sum before this change | $520,000 |
| This agreed change | $8,000 |
| Revised contract sum | $528,000 |
Price and time need separate decisions
A priced scope change is not automatically a time extension. Identify the affected operation, current schedule reference and why the change may affect completion or sequencing. The reviewer needs more than a statement that “extra work takes time.” Conversely, agreeing a price should not accidentally imply that all time effects have been waived.
For an illustrative agreed extension of three calendar days from October 30, the revised date is November 2, 2026. Use the contract’s actual calendar convention and approved schedule when completing a real form. If time remains unresolved, do not present an executed instrument as full agreement without checking how the contract permits that issue to be handled.
The daily record does not replace notice
Save photos, crew updates, instructions and delivery evidence while the facts are fresh. Then check the contract’s notice recipient, method and trigger. Under unmodified AIA A201–2017 §15.1.3.1, the specified category of claims generally has a 21-day initiation period after the event or first recognition of the condition, whichever is later. That is not a universal change-order deadline.
AIA §15.1.5 also requires additional-cost claim notice before executing the affected work, except its stated emergency exception. Do not assume the 21-day provision permits waiting until work is finished. Amendments and subcontract provisions may change the applicable procedure; get qualified advice on disputed entitlement.
Text Magra to draft one
Send the project number the instruction, affected area, photos and known resources. Magra can organize the field evidence and prepare a change order draft for your review. Project documents provide context for follow-up questions; missing rates or quantities should be requested, not guessed.
Nothing about a generated draft makes it approved. The contractor reviews it, checks the scope and notice requirements and obtains the required agreement. Magra keeps the paperwork moving while the construction team remains responsible for the commercial decision.
Common questions
Can a change order have no cost increase?
Yes. It can record an agreed change with no price adjustment, a credit or an increase. Time adjustments are considered separately.
Is a change order request the same as a change order?
No. A request or proposal seeks agreement. An executed change order records the agreement and required signatures.
Can work be directed before a change order is agreed?
Under AIA A201–2017, a valid construction change directive can require prompt performance before total agreement on price or time. Check your actual contract.
Sources & editorial note
By Magra editorial. Examples are illustrative, not customer results. Not legal advice; executed documents, amendments and applicable law govern. Product availability can change.