A ticket proves the record; it does not settle every issue
Time-and-materials work is easy to argue about after the crew leaves. A good ticket makes the daily resources visible while the GC can still verify the location, operation and people involved. It helps answer “what was used?” separately from “was this authorized extra work?” and “what rate is payable?”
This guide is for subcontractor documentation. The actual subcontract controls authorization, ticket submission, allowable costs and who can sign. AIA A201–2017 §7.3.4 requires itemized accounting and supporting data where its cost-determination process applies, but it does not establish a universal daily-signing requirement or ticket submission deadline for every subcontract.
Write a ticket that can be checked on site
Keep base-scope production out of an extra-work ticket unless the allocation is explained. If the same crew works on both, show the separation of hours. Avoid one line such as “four men, one day, extra work” when the work area, operation and actual time can be specified.
- Project, ticket number, work date, shift and precise location.
- Directive, change request or other authorization reference.
- Specific operation and why it is being recorded separately from base scope.
- Labor classification and regular/overtime hours, with appropriate supporting time records.
- Equipment identifier, use and operating or idle hours recorded separately.
- Materials, quantities, units and delivery or invoice references.
- Photos and sketches that identify the work and area.
- Preparer, reviewer, signature scope, date and any exceptions.
An illustrative ticket entry
Downtown Office Tower | T&M-014 | October 20, 2026 Area: Level 6 east corridor Instruction reference: Field instruction FI-07, authorization status to be checked against subcontract Work: Relocate conduit around revised opening; base-scope installation excluded Labor: 2 electricians × 3 regular hours = 6 person-hours Equipment: Lift L-03, 2 operating hours; idle time listed separately if applicable Materials: 30 linear feet conduit, 8 couplings; delivery reference D-118 Evidence: Photos P-031–P-033; marked-up sketch S-04 Reviewer acknowledgment: State the observed quantities/hours confirmed and any exceptions Commercial approval: Separate review of entitlement, rates, markups, price and time
Be explicit about what the signature means
A reviewer may be able to confirm observed hours and materials without having authority to approve a change price or time extension. Label the intended acknowledgment clearly and check who is permitted to provide it. Do not assume a superintendent’s signature creates authority the contract gives to a project executive.
A signature’s effect depends on wording, authority, contract terms and circumstances. An acknowledgment limited to observed quantities is not necessarily approval of entitlement, rates or payment. Conversely, do not promise that every ticket signature is “receipt only.” A contractor-signed A201 CCD has an express agreement effect under §7.3.7, which is a different instrument.
Build the price from supported records
Reconcile labor to the underlying time records, materials to invoices and equipment to the agreed rate basis. Confirm whether labor burdens, supervision, small tools, taxes and markups are included in a rate or charged separately. Avoid duplication and use the cost treatment allowed by the contract.
A ticket may record quantities before all rates are agreed. Show that status instead of making a draft total appear approved. If the subcontract requires a particular ticket format, daily presentation or submission channel, follow it. There is no universal 24-hour deadline that this guide can substitute for your documents.
What if the GC will not sign?
Ask what is disputed: the work direction, the hours, the materials, the reviewer’s authority or the commercial terms. Record the response accurately and submit the supporting evidence through the required channel. Keep the original ticket, photos, time records and correspondence.
An unsigned ticket is not automatically worthless, and a signed ticket is not automatically conclusive. Neither condition replaces timely notice where the contract requires it. Avoid an unsupported statement that silence means acceptance. For a material dispute, have the responsible project manager and qualified adviser review the next step.
Capture the ticket facts before they disappear
Text Magra the work area, instruction reference, crew hours, equipment and photos while the operation is fresh. Magra can ask about missing quantities and organize a draft with the project’s supporting records. Your office checks the rates, authorization and signature wording before sending it.
This is where a project-specific knowledge base matters. The right rate card and instruction belong to the right job. A draft should flag missing commercial information, not copy a rate from another project or guess what the GC agreed.
Common questions
Does a signed T&M ticket guarantee payment?
No. Its effect depends on the signature wording, authority, contract and facts. Observed hours may be acknowledged while entitlement or pricing remains unresolved.
How quickly should a T&M ticket be submitted?
Follow your subcontract’s deadline and channel. As a practical matter, present records while the reviewer can still verify the work, but there is no universal deadline.
Can I document work if the reviewer refuses to sign?
Yes. Preserve the ticket and contemporaneous supporting records, record the refusal accurately and follow your required submission and notice process.
Sources & editorial note
By Magra editorial. Examples are illustrative, not customer results. Not legal advice; executed documents, amendments and applicable law govern. Product availability can change.